As you can see, we have started the pond project. We drained the pond on Thursday and Friday. Now we are working to remove all the concrete around the spill way. We discovered a beautiful stone wall underneath the concrete. We are trying to restore that instead of building a new one. Will be giving more updates later this week!
Starting yesterday, the construction crew began sodding the 18th green complex. They have installed bentgrass for the fairway extensions, low cut bluegrass for the intermediate cut and turf type tall fescue for the rough. They also installed some fine fescue on the bunker edges. We plan to finish sodding by tonight but might need to purchase a small quantity more next week to fix some construction wounds.