As you can see in this picture, we are installing the internal drainage
in the green cavity. Our goal is to finish it today and then start
adding the greens grade soil. We plan to to complete the finish grade of
the green surface by Monday afternoon. We plan to install the green sod
on Tuesday. The irrigation for the green is almost complete and will
have water in it by tomorrow.
Starting yesterday, the construction crew began sodding the 18th green complex. They have installed bentgrass for the fairway extensions, low cut bluegrass for the intermediate cut and turf type tall fescue for the rough. They also installed some fine fescue on the bunker edges. We plan to finish sodding by tonight but might need to purchase a small quantity more next week to fix some construction wounds.