Llanerch received 6.3 inches of rain! We have seen over 70% of the bunkers washed out. We are working now to redistribute sand in the bunkers, cleanup mulch piles and pick up debris by creeks and ponds. This is the second time in less then 3 years we have had a storm with over 6 inches of rain. What used to be every 50 or 100 years is becoming every 3-5 years!
Starting yesterday, the construction crew began sodding the 18th green complex. They have installed bentgrass for the fairway extensions, low cut bluegrass for the intermediate cut and turf type tall fescue for the rough. They also installed some fine fescue on the bunker edges. We plan to finish sodding by tonight but might need to purchase a small quantity more next week to fix some construction wounds.