Yesterday we finished edging out the three bunkers surrounding the green and rough shaping the new fairway. We are planning to install drainage in them on Monday. We will also begin edging and draining the new fairway bunker on Monday. Sodding of the entire green surround will begin on Wednesday. Of course, this all is weather dependent. A snow storm could potential push the whole schedule back a few days.
Starting yesterday, the construction crew began sodding the 18th green complex. They have installed bentgrass for the fairway extensions, low cut bluegrass for the intermediate cut and turf type tall fescue for the rough. They also installed some fine fescue on the bunker edges. We plan to finish sodding by tonight but might need to purchase a small quantity more next week to fix some construction wounds.