Skip to main content

#9 and the Drone

As you can see in the top left of this picture, we were taking pictures with a drone for the construction of #9 green. Aradar Tree Service remove some large pines to the right of the green. The Grounds Staff will remove the remaining spruces and hedges around the green. The driveway and fence line along the right of #9 will have a new hedge installed in the latter part of October. Construction starts October 4th, weather dependent.

Popular posts from this blog

Sod, Sod, Sod

Starting yesterday, the construction crew began sodding the 18th green complex. They have installed bentgrass for the fairway extensions, low cut bluegrass for the intermediate cut and turf type tall fescue for the rough. They also installed some fine fescue on the bunker edges. We plan to finish sodding by tonight but might need to purchase a small quantity more next week to fix some construction wounds. 
With the help of architects Brian and Blake, we are now seeing what the new bunkers look like. This one is on 10 green right side. They will not have the fescue "eyebrow" we have had in the past. For more updates, please follow me @BrendanJByrne01 on Twitter.